Zip to the Airport Forget about battling through Bangkok traffic to catch your filght. From December you will be able to check in at the City Air Terminal in Makkasan and even get your boarding pass Riding a fast Skytrain to the airport will soon be a new lifestyle for outbound travellers. The long-awaited Airport Link will be functional by this December. Travellers will have the option of checking in their luggage at the soon-to-be-opened City Air Terminal (CAT) in the Makkasan area before boarding the rapid train to Suvarnabhumi Airport with their carry-on bags. The CAT, 270 metres by 70 metres, has three floors where passengers can board a train as well as check in, receive a boarding pass and leave their luggage on the third floor. The luggage will be transferred to their flight. The second floor will be for arriving passengers and the first a parking lot for 200 cars. The luggage will be transferred by Suvarnabhumi Airport Express (SA-Express) and placed in a designated coach while passengers will board other coaches on the same train. A source says the Makkasan Station is expected to be completed by October this year. Finishing touches The main structure is already finished. Workers are now decorating each floor, while the modern-style roof of the station is nearly complete. Motorists on the expressways near the station can already see the attractive design of the roof. The four rail tracks for the SA-Express and Suvarnabhumi Airport City Line and another train serving commuters are well into construction. The tracks will allow trains to reach speeds of up to 160kph. Express journeys will take 15 minutes and commuter trips 27 minutes. The station is part of the Airport Rail Link Project, expected to be officially opened by December. The estimated cost of the project is Bt25.9 billion. Engineer Banchongsak Panthong said last month that 78.5 per cent of the construction had been completed and 82 per cent of electrical and mechanical work. >> Suvarnabhumi Airport - Lad Krabang - Thub Chang - Hua Mark - Ramkhamhaeng - Makkasan (City Air Terminal - interchange with MRT Blue Line's Phetchaburi Station) - Ratchaprarop - Phayathai (interchange with BTS Sukhumvit Line's Phayathai Station) http://www.nation...070326.php |
|
|
|
| Payanak |
Lagt på d. 14/05-2008 11:24
|
|
Ekspert medlem ![]() Antal indlæg: 2597 |
Airport Link set for more delays Contractor Stecon wants 370 more days The contractor for Bangkok's Airport Link is seeking a one-year extension to complete the 26-billion-baht project, blaming slow land transfers from the State Railway of Thailand (SRT). The delay is subject to approval by the SRT board on May 26, according to Sino-Thai Engineering & Construction Plc (Stecon), which leads the consortium building the rail line to Suvarnabhumi Airport. Tawatchai Sintoplertchaiyakul, Stecon's project manager for the Airport Link, said the company would need an additional 370 days to complete civil works, followed by 90 days to integrate all systems. The previous government had earlier approved a 180-day extension for the contractor to complete the project by Feb 4 this year. So far, construction of the rail link is about 84% complete, Mr Tawatchai said. ''We need more time to get the civil works done because of the delayed land transfers,'' he said. [img]http://www.bangkokpost.com/Business/140508_bus01.jpg[/img] is not a valid Image. Construction is advancing steadily but problems with land transfers have delayed the 26-billion-baht megaproject. Parcels of land along a 1.2-kilometre stretch between the route's Phaya Thai and Ratchaprarop stations were transferred to the contractor 22 months behind the original schedule, he added. Stecon and B. Grimm were awarded the civil works contract worth 12.3 billion baht for the 28-kilometre route from Phaya Thai to the airport. Another consortium partner, Siemens AG, has a 13.6-billion-baht contract to develop tracking and signalling systems and supply train carriages. Construction started in mid-2005. Prior to the extension, the rail link was scheduled to be transferred to SRT in November of this year, he said. While admitting the cause of the delays, SRT spokesman Watcharachan Sirisuwannatash said the agency's board would consider the extension of the contract based on existing information. After construction is completed, the project would require another six to seven months of testing and project commissioning. Tentatively, the rail link is expected to start service in December 2009, Mr Watcharachan said. The Airport Link would offer two types of service on parallel rails with the City Line stopping at every station to transport passengers from Phaya Thai to Suvarnabhumi in 30 minutes. The non-stop Airport Express would run from Makkasan to the airport in 15 minutes. The train would have a maximum speed of 160 kilometres per hour. Mr Watcharachan added that the board on May 26 would also consider an investment of about 90 million baht to connect the Airport Link with the Phetchaburi subway station and the Phaya Thai BTS station. The resolution is subject to final approval from the cabinet. Mr Tawatchai said the delays had forced the builders to shoulder rising costs of construction materials, especially steel. Costs are also expected to rise with increases in the minimum wage next month. SET-listed Stecon posted a net profit of 21.67 million baht in 2007 against a loss of 1.77 billion a year earlier when the company booked all losses stemming from construction of long-term projects including the Airport Link. Total revenue increased from 14.8 billion baht in 2006 to 17.47 billion baht last year. CIMB-GK Securities (Thailand) said that high steel prices had put pressure on Stecon's results. Steel prices went up 18% year-on-year in the last quarter of 2007 and another 34% in January. Cement and steel prices are expected to rise 10% in 2008, and CIMB has cut its earnings forecast for Stecon by 60% this year. Stecon shares (STEC) closed at 4.88 baht yesterday, down 0.81%, in trade worth 22.89 million baht. http://www.bangko..._biz31.php |
|
|
|
| Spring til debat: |








. Det er fanme alverdens ting man kan få lavet nu om dage. 